آخرین محصولات

Rates Analysis For Calculating Material and Labour for ...

Rates Analysis For Calculating Material and Labour for building works 1. By .Ali Hyder Gadhi 2. ANALYSIS OF RATES • To determine the rate of a particular item of work from a quantities of materials and labours required and their costs • The rates of materials and labour are changing from place to place, therefore the rates o different items of work also changes from place to place

كوبي اولیه برای مرحله خوب مخرب، regrinding، و به عنوان مرحله…

Downloaded from ascelibrary by Hong Kong Polytechnic ...

For concrete placement, labor productivity can be expressed as hours per cubic meter or cubic meters per hour. The ratio can be in the format of input/ output. As demonstrated in Eq. (1), CLP is measured in actual work hours per installed quantity; specifically, this pertains to the number of actual work hours required to perform the ...

كوبي اولیه برای مرحله خوب مخرب، regrinding، و به عنوان مرحله…

how many labour need to pour 100 cubic meters concrete ...

how to calculate labour cost for concrete work per cubic meter.. 1.95 m/m, .68 f/m, .27 bh, .05 first class mason, .05 second class mason … Re: HOW TO CALCULATE LABOUR COST FOR CONCRETE WORK PER CUBIC METER.Answer … Answer # 4, Please tell me How many Cum can do a mason. if you know … Answer # 6, for the rates of all labours, masssons etc we have to check …

كوبي اولیه برای مرحله خوب مخرب، regrinding، و به عنوان مرحله…

How much cement do I need for 1 cubic metre of concrete ...

The Labour cost for concrete work is around 70 to 75 Rs per cft (cubic foot) or 2500 to 2650 Rs per cubic meter (m3). The Labour Cost for PCC concrete is around 30 to 35 Rs per sq ft (square foot) or 320 to 400 Rs per cubic meter (m3). How much concrete does a 40kg bag of cement make? Using proportions suggested, one 40 kg (88 lb) bag of cement ...

كوبي اولیه برای مرحله خوب مخرب، regrinding، و به عنوان مرحله…

How much labour is required for excavating the soil of 1 ...

Answer (1 of 5): A good man can dig a cube of soil out in a morning. If harder soil, such as heavy clay, it takes all nearly day. A JCB will dig a cube out in a few minutes. A 300 PC in a few seconds.

كوبي اولیه برای مرحله خوب مخرب، regrinding، و به عنوان مرحله…

Analysis & Rates, Analysis and rates for construction work ...

b) Cement concrete work per 2.83 cum (100cuft) laying cement concrete – 2 beldars, 3 mazdoors, ¾ bhisti and ¼ mason, can do 2.83 cum (100 cuft) per day. c) R C C work:- 1) Laying reinforced concrete – 3 beldars, 3 mazdoors, 1½ Bhisti and ½ mason can do 2.83 cum (100cuft) per day.

كوبي اولیه برای مرحله خوب مخرب، regrinding، و به عنوان مرحله…

How to Calculate Number of Labour Required for Manual ...

Suppose we want to excavate 100 square meter area (Depth not exceeding 300 mm) manually.. In CPWD – DAR, it is given that for 1 Square meter, the Co-efficient of labour is 0.124. So, for 100 Square meter excavation, Labour required = 100 x 0.124 = 12.4 Numbers. Suppose if you have to complete the given work in two days, then Labour required per day = 12.4 / 2 = 6.2

كوبي اولیه برای مرحله خوب مخرب، regrinding، و به عنوان مرحله…

How much quantity of steel required for 1m3 concrete ...

1) thumb rule for steel in rcc slab is 80 kg/cubic meter of wet volume of concrete. 2) thumb rule for steel in beam is 120 kg/cubic meter of wet volume of concrete. 3) thumb rule for steel in column is 160 kg/cubic meter of wet volume of concrete. 4) thumb rule for steel in footing is 40 kg/cubic meter of wet volume of concrete. 5) thumb rule ...

كوبي اولیه برای مرحله خوب مخرب، regrinding، و به عنوان مرحله…

How to Estimate Concrete Costs? - The Constructor

In this article we calculate the cost of 1 cubic meter of concrete and other expenses that occur in the preparations of concrete. ... Cost of sand for 1 m 3 = As per latest market rate, cost of 1 m 3 of sand is taken as Rs: 1400 = 0.42 X 1400 ... Labours finishing the concrete work. Read More: 8 Types of Cost Estimates in Construction. Share ...

كوبي اولیه برای مرحله خوب مخرب، regrinding، و به عنوان مرحله…

Labor Requirement for Various Construction Works - The ...

S. No. Description of work: Unit: Labor: Recommended constant in days. 1) Excavation over areas (hard/dense soil),depth up to 1.5m and removal (up to one meter from edge): M 3: Mate Labor. 0.06 0.62. 2) Excavation in trenches (soft/ loose soil),for foundations not exceeding 1.5m in width and for shafts, wells, cesspits and the like, not exceeding 10m3 and on plan, depth up to 1.5m and …

كوبي اولیه برای مرحله خوب مخرب، regrinding، و به عنوان مرحله…

Estimating Excavation Revised

Today, fuel and labor costs are too high and the competi - tion is too intense to risk "seat-of-the-pants" guesses. A few mistakes and a couple of surprises and you're going to be looking for some other type of work. Only the best survive for long in this business. And most of the survivors know how to make accurate bids by the cubic yard.

كوبي اولیه برای مرحله خوب مخرب، regrinding، و به عنوان مرحله…

How many concrete blocks are required for 1 cubic meter ...

Answer (1 of 9): Mr. question ire you have typed not specific question about blocks, so the main question should be 1. what is the standard size of concrete blocks? 2. how many blocks require for 1 cubic mtr? ans- size of blocks used in construction industry are not specific its upon structura...

كوبي اولیه برای مرحله خوب مخرب، regrinding، و به عنوان مرحله…

What Is In 1 Cubic Metre Mix of Concrete? [Infographic ...

What Is In 1 Cubic Metre Mix of Concrete? Concrete is one of the most versatile construction materials available, and by far the most popular. Used for an endless variety of building projects, there is a huge range of concrete mixes to suit specific applications, so the proportions of each mix need to be measured with precision.. If you need concrete for your project, call our team on 0800 859 ...

كوبي اولیه برای مرحله خوب مخرب، regrinding، و به عنوان مرحله…

Concrete Work in Excel | Labor Costs Calculation ...

To start the work, initially you have to create a detail table that contains various heads like serial number, quantity of labor for each 10 cubic meter of work, rate per day (8 hours) and total amount.

كوبي اولیه برای مرحله خوب مخرب، regrinding، و به عنوان مرحله…

How much does concreting cost? | 2020 Cost Guide | Service ...

Choice of concrete. The concrete you choose to work with will impact upon your price. As mentioned, spray on concrete costs $50 to $75 per square metre, plain concrete costs $60 to $85 per square metre. coloured concrete costs $100 to $150 per square metre and exposed aggregate or decorative stencilled finish costs $100 to $150 per square meter.

كوبي اولیه برای مرحله خوب مخرب، regrinding، و به عنوان مرحله…

CHAPTER 5 ESTIMATING WORK ITEMS COSTS, IDIRECT COSTS ...

It is required to determine the unit price for plain concrete given the following information: Plain concrete (PC) quantity = 1080 m3. One cubic meter of PC comprises of 250 kg cement; 0.8 m3 gravel and 0.4 m3 sand. The prices of these materials are LE500/ton; LE80/m3 …

كوبي اولیه برای مرحله خوب مخرب، regrinding، و به عنوان مرحله…

Rate Analysis of Plain Cement Concrete ... - CIVIL WORK STUDY

For 1m3 of wet or solid Plain Cement Concrete (PCC) ratio (1:3:6), we have to multiply with factor 1.52 for dry density than 1m3 become 1.52m3 of cement, sand & aggregate is required, due to presence of voids in sand in dry state. So, cement sand and aggregate quantity is calculated for 1.52m3 of PCC. Dry volume = 1.52 m3.

كوبي اولیه برای مرحله خوب مخرب، regrinding، و به عنوان مرحله…

ESTIMATING LABOR UNIT DATA FOR CONCRETE …

would be evaluated by multiplying $3.572 by 1.05, which equals $3.75: composite rate for 65 percent pro d u c t i v i t y . Simply by multiplying the number of manhours esti-mated for a given block or item of work by the arri v ed at composite ra t e, a total estimated direct labor cost, in dollar va l u e, can easily and accurately be obtained,

كوبي اولیه برای مرحله خوب مخرب، regrinding، و به عنوان مرحله…

how to calculate cost of concrete per cubic meter

How To Calculate Labour Cost For Concrete Work Per Cubic Meter. The cost of concrete per cubic metre in Australia is anywhere from $200 - $300+ per m3 (cubic metre), though you could pay as much as $350 for 40 MPa strength. Variations in cost will be due to local prices differing slightly, the type of concrete you order as … Learn More

كوبي اولیه برای مرحله خوب مخرب، regrinding، و به عنوان مرحله…

Rate analysis for M20 concrete - Civil Sir

Labour rate and charges Rs. 600 :- consider one mason and 2 helper completed 1 cubic metre of concrete work in 4 hours, labour cost will be Rs. 600 Sub total cost = 5680 + 600 = INR 6280 Water charges of Rs 94:- quantity of water required in concreting work used for preparing of mix and curing, consider 1.5% cost of water, then 1.5% of 6280 = Rs.94

كوبي اولیه برای مرحله خوب مخرب، regrinding، و به عنوان مرحله…

Labor Requirement for Various Construction Works - The ...

S. No. Description of work: Unit: Labor: Recommended constant in days. 1) Excavation over areas (hard/dense soil),depth up to 1.5m and removal (up to one meter from edge): M 3: Mate Labor. 0.06 0.62. 2) Excavation in trenches (soft/ loose soil),for foundations not exceeding 1.5m in width and for shafts, wells, cesspits and the like, not exceeding 10m3 and on plan, depth up to 1.5m and removal ...

كوبي اولیه برای مرحله خوب مخرب، regrinding، و به عنوان مرحله…

How to Calculate Cement, Sand and Aggregate required …

From above, if the concrete mix is 1:2:4, to get a cubic meter of concrete we require. 1.Cement = 6 bags = 300 kgs. 2.Fine Aggregate = 115/0.167 = 689 kg. 3.Coarse Aggregate = 209/0.167 = 1252 kg. 4.Water = 300/0.55 = 165 kg. Like wise other concrete mix with varying proportions and materials with different physical properties,the individual ...

كوبي اولیه برای مرحله خوب مخرب، regrinding، و به عنوان مرحله…

Rate analysis for concrete - calculate quantity and cost ...

step 6, labour rate and charges :-consider one mason and 2 helper completed 1 cubic metre of concrete work in 8 hour, per mason rate INR 600 and per Helper rate 400,then cost of labour in concreting work = 600 +(2×400) = INR 1400.

كوبي اولیه برای مرحله خوب مخرب، regrinding، و به عنوان مرحله…

How much ballast do I need for a cubic Metre of concrete ...

How many 20kg bags make a cubic meter? 108 x 20kg bags one 20kg bag will cover an area of 1.1m2 to a depth of approximately 10mm. or 108 x 20kg bags equates to one cubic metre of mixed concrete. What is the cost of 1m3 of concrete? The Labour cost for concrete work is around 70 to 75 Rs per cft (cubic foot) or 2500 to 2650 Rs per cubic meter (m3).

كوبي اولیه برای مرحله خوب مخرب، regrinding، و به عنوان مرحله…

Estimating Costs for Concrete Formwork, Rebar, Labor, and ...

Concrete pricing is typically quoted per cubic yard or cubic meter (metre). For an average estimating number, you can use $77 per cubic yard. Cost of Concrete Sub-Grade Work. ... Building concrete forms usually represents a significant portion of the total cost of concrete work, as this is one of the most labor-intensive aspects of the job.

كوبي اولیه برای مرحله خوب مخرب، regrinding، و به عنوان مرحله…

ArchiDesigners : Calculation of material and labour ...

Sand = 1.50 Cu Note: When we issue the payments for the labours, consider only the actual volume of rubble masonry and not the amount of purchasing of rubble. Therefore, payment should be issued for labour for this work is 4.77 cu (Skilled labour days …

كوبي اولیه برای مرحله خوب مخرب، regrinding، و به عنوان مرحله…

askEngineerOsaz': Current Construction Workers' Labour ...

Fantastic work you're doing Engr Osaz. However, a bit of reservation on the concrete casting rate. Generally it goes with the volume being dealt with and also, the work section. Strategically, one can achieve concrete casting for 4000/m3 depending on your work flow and bargaining power. Reply Delete

كوبي اولیه برای مرحله خوب مخرب، regrinding، و به عنوان مرحله…

ESTIMATING LABOR - tpub

Another method you may use to calculate this is as follows: In this equation, you simply cross multiply the following: 160 x 448 = 71680. X times 1000 = 1000 x, then divide. 71680 ÷ 1000 x. X = 71.68 or 72 MH. In this example, it takes 72 man-hours to lay 448 SF or 504 CMUs. Now divide the number of …

كوبي اولیه برای مرحله خوب مخرب، regrinding، و به عنوان مرحله…

How to calculate the Labor, equipment, shuttering & rebar ...

1- material. 2- labour charge. material means :1- concrete price and that depend of wat element u want to cast it sub or super struc. and is it required green concrete or SRC or OPC approxmately it will be around AEd255 if its green concrete. oAed 215 if it SRC for mix 400 kg grade 40 n. also pump charge will be assume 50/m3

كوبي اولیه برای مرحله خوب مخرب، regrinding، و به عنوان مرحله…

Estimating Costs for Concrete Formwork, Rebar, Labor, …

1- material. 2- labour charge. material means :1- concrete price and that depend of wat element u want to cast it sub or super struc. and is it required green concrete or SRC or OPC approxmately it will be around AEd255 if its green concrete. oAed 215 if it SRC for mix 400 kg grade 40 n. also pump charge will be assume 50/m3

كوبي اولیه برای مرحله خوب مخرب، regrinding، و به عنوان مرحله…